Manufacturing Engineering · Quick practice · answer shown after each question

Costs and supply

Question 1 of 10

Question 1 of 10

Fixed costs GH¢50,000; variable cost GH¢30/unit; price GH¢55/unit. Break-even output is

Question 2 of 10

Question 2 of 10

Inventory held as a safety buffer is called

Question 3 of 10

Question 3 of 10

Raw materials bought but not yet used are part of

Question 4 of 10

Question 4 of 10

Costs that do not change with output, such as factory rent, are

Question 5 of 10

Question 5 of 10

The network of suppliers, manufacturers, distributors and retailers that moves a product to customers is the

Question 6 of 10

Question 6 of 10

Unit cost is

Question 7 of 10

Question 7 of 10

Ghana's One District, One Factory programme aims mainly to

Question 8 of 10

Question 8 of 10

Fixed costs are GH¢10,000 and the variable cost is GH¢5 per unit. What is the total cost of 2,000 units?

Question 9 of 10

Question 9 of 10

Transport, storage and delivery of goods are part of

Question 10 of 10

Question 10 of 10

A product sells for GH¢15, costs GH¢10 per unit to make, and fixed costs are GH¢5,000. What is the break-even quantity?

Questions written by OtisamLMS in the style of the WASSCE. They are not WAEC past questions.