The process of marking out the positions of walls on site before excavation is
Question 2 of 50
The part of a building that transfers its load to the ground is the
Question 3 of 50
Concrete is made by mixing
Question 4 of 50
Keeping fresh concrete moist for several days so it gains strength is
Question 5 of 50
Steel bars placed in concrete to resist tension are called
Question 6 of 50
Sandcrete blocks are made from
Question 7 of 50
A course of bricks laid with their long faces showing is a
Question 8 of 50
The layer that stops ground moisture rising up a wall is the
Question 9 of 50
A horizontal member over an opening that carries the load above it is a
Question 10 of 50
The tool used to check that a wall is vertical is the
Question 11 of 50
The timber member that forms the sloping side of a pitched roof is the
Question 12 of 50
The highest horizontal line of a pitched roof is the
Question 13 of 50
A thin layer of cement and sand mortar applied to walls to give a smooth finish is
Question 14 of 50
A temporary platform used to work at heights during construction is a
Question 15 of 50
Which item of protective equipment protects the head on a building site?
Question 16 of 50
Clearing vegetation and topsoil from a building site is
Question 17 of 50
The 3-4-5 method in setting out is used to obtain
Question 18 of 50
Profile boards are used to
Question 19 of 50
The most common type of foundation for a small house on firm soil is the
Question 20 of 50
The instrument used to transfer levels across a site is the
Question 21 of 50
A concrete mix of 1 : 2 : 4 means
Question 22 of 50
Temporary moulds that hold wet concrete until it sets are
Question 23 of 50
A bond in which header and stretcher courses alternate is the
Question 24 of 50
The bottom horizontal member of a window frame that throws water off the wall is the
Question 25 of 50
The horizontal timber fixed on top of a wall to receive the roof rafters is the
Question 26 of 50
The board fixed to the ends of the rafters at the eaves is the
Question 27 of 50
A roof that slopes on all four sides is a
Question 28 of 50
A layer of mortar laid on a concrete floor to give a level, smooth surface is a
Question 29 of 50
The timber board fixed at the bottom of internal walls to protect them is the
Question 30 of 50
The pipe that carries waste water from sinks and basins to the drain is the
Question 31 of 50
A raft foundation is most suitable where
Question 32 of 50
The slump test is used to measure the
Question 33 of 50
A bond with headers and stretchers alternating within the same course is the
Question 34 of 50
Pile foundations are used where
Question 35 of 50
A queen closer is
Question 36 of 50
Differential settlement in buildings causes
Question 37 of 50
The water–cement ratio mainly affects concrete's
Question 38 of 50
Honeycombing in concrete is caused by
Question 39 of 50
Wall ties in cavity walls are used to
Question 40 of 50
Timber suspended floors need underfloor ventilation to
Question 41 of 50
The volume of excavation for a trench 20 m long, 0.6 m wide and 0.9 m deep is
Question 42 of 50
The characteristic strength of concrete is usually tested at
Question 43 of 50
A wall 10 m long and 3 m high uses 10 blocks per m² (ignoring openings). The blocks needed are
Question 44 of 50
Movement joints in long walls are provided to
Question 45 of 50
The safe bearing capacity of a soil is 150 kN/m² and the wall load is 300 kN per metre. The minimum strip width is
Question 46 of 50
How many bags of cement (50 kg) are needed for 1 m³ of 1:2:4 concrete if dry volume is 1.54 m³ and cement density is 1,440 kg/m³?
Question 47 of 50
A one-brick wall in English bond is about
Question 48 of 50
A roof with a span of 8 m and pitch of 30° has a rise of about (tan 30° ≈ 0.577)
Question 49 of 50
The minimum fall for a 100 mm drainage pipe is about
Question 50 of 50
Concrete cubes 150 mm fail at 675 kN. The compressive strength is